Earlier today (02/10/2014) I went by the house twice, once after work, and once around 5:00 PM. The trades were starting to install the plumbing and had installed the HVAC equipment. I also got a chance to talk to my sales rep, and the issues with the specs sheet are in the process of being addressed (they were working off an old copy at the site). He is e-mailing the project manager to make sure they do not put almond bathroom fixtures. He also told me that he got a call from the project manager about the bronze hinges and door knobs. The electrical issues are just due to the old build sheet, he showed me the most current copy, and everything was correct on that one. Below are pictures of today's progress. I hope that the impending major snow event does not slow us down too much.

HVAC hoses in the attic space.

More detail of the framing for the tray ceiling.

top floor HVAC in the attic space

Plumbing contractor parked in the future front yard.

No comments: