Saturday, February 15, 2014

This weeks wild weather.

Since I last posted, the plumbing trades and HVAC trades have finished their work at this stage, though I noticed one issue that is going to have to be brought up at the walkthrough, unless I catch my project manager head of that. I had put in a request to have a hose bib at deck level. It was located next to the patio door. I don't think it will be a big deal to have one run at this point.

On Monday morning I am going to be meeting with Guardian to finalize the rough in locations for my multitude of wiring I paid for. I also know the electrician is going to be starting my house either Monday afternoon or on Tuesday morning. I do have some concerns about them getting the spacing right for my ceiling lighting in the living room and recreation room, otherwise everything is pretty standard, except for adding a few dedicated circuits and electrical outlets.

The masonry trades were starting to the brick on the end unit of my row. However, it was slow progress for them due to the amount of snow. Hopefully with the warmer weather this coming week, we will start to see the outside of the home really shape up.




Lennox MPD40 Fireplace.

Gas line runs straight front to back, then over for the fireplace. Good to know if I want to make my grill natural gas.

No comments:

Post a Comment